Requirement:
When a routing is changed, it must be possible to replace it in the production process. We can change the following things:

  • Operations
  • Resources for operations
  • Times After changing the Routing there should be a possibility to choose whether we change it in every process or only in selected ones.
StepActionObilgatory
1In B1/PF prepare modified Routing's template (define new Code by adding e.g. Revision ID) with changes in: Operations, Resources, times, etc. It is recommended to put some additional information in Remarks (the scope of changes).YesRouting changing for selected processes
2Open Bulk Changes from AppEngine or directly from B1/PF, create new scenario and Select Change Scope = RoutingsYes
Click here to expand
3In Selected BOMs tab select BOMs (processes) for which the routing have to be changedYes
Click here to expand
4In Routings tab filter and select routing which has to be replaced. Choose mode Replace and select routing (prepared in step 1) as a Replacement. At the end you can unselect some processes. The change will not affect them.Yes
Click here to expand
5Add ScenarioYes-
6Start process of bulk changes preparationYes
Click here to expand
7Check if the changes are correct in Proposed Changes tabYes
Click here to expand
8Execute the scenarioYes
Click here to expand
9Check results of bulk changes in Proposed Changes tab and in B1/PFRecommended